MILESTONES OF THE PROJECT |
| |
|
|
| |
|
• Project approved in the supplementary Railway Budget 2006-07. |
| |
|
• Foundation stone laid by the Hon'ble Chairperson, UPA Smt. Sonia Gandhi-13th Feb, 2007 |
| |
|
• Land acquisition activities started - 10th Aug, 2007 |
| |
|
• Land lease deed signed with Uttar Pradesh Govt - 16th Jan, 2009 |
| |
|
• Inauguration of construction of factory boundary wall by the Hon'ble Chairperson, UPA Smt. Sonia Gandhi - 27th Jan, 2009 |
| |
|
• Completion of Factory Boundary Wall - Dec, 2010 |
| |
|
• Completion of Rail Connectivity - Jan, 2011 |
| |
|
• Completion of Overhead Water Tanks - Nov, 2010 |
| |
|
• Commissioning of 33 KV Transmission line & substation - Jan, 2011 |
| |
|
• Start of earthwork for Factory Construction - 26"1 May, 2010. |
| |
|
• Roads for Phase I - Started - Oct 2010, Completed - Mar, 2011. |
| |
|
• Finishing Shop - Started - Sept 2010, Completed - Feb, 2011. |
| |
|
• Furnishing Shop - Started - Sept 2010, Completed - Apr, 2011 |
| |
|
• Major M&P of Phase I commissioned - Mar, 2011 |
| |
|
• Temporary Housing - Started - Oct 2010, Completed - Jan, 2011 |
| |
|
• Phase-I Production (First coach ready) - 8" April, 2011 |
| |
|
• No. of Permanent Type-ll houses completed - 104 |
| |
|
• No. of Permanent Type-Ill houses completed - 8 |