    MILESTONES OF THE PROJECT
     
  • Project approved in the supplementary Railway Budget 2006-07.
    • Foundation stone laid by the Hon'ble Chairperson, UPA Smt. Sonia Gandhi-13th Feb, 2007
    • Land acquisition activities started - 10th Aug, 2007
  • Land lease deed signed with Uttar Pradesh Govt - 16th Jan, 2009
  • Inauguration of construction of factory boundary wall by the Hon'ble Chairperson, UPA Smt. Sonia Gandhi - 27th Jan, 2009
  • Completion of Factory Boundary Wall - Dec, 2010
    • Completion of Rail Connectivity - Jan, 2011
  • Completion of Overhead Water Tanks - Nov, 2010
  • Commissioning of 33 KV Transmission line & substation - Jan, 2011
  • Start of earthwork for Factory Construction - 26"1 May, 2010.
  • Roads for Phase I - Started - Oct 2010, Completed - Mar, 2011.
  • Finishing Shop - Started - Sept 2010, Completed - Feb, 2011.
  • Furnishing Shop - Started - Sept 2010, Completed - Apr, 2011
    • Major M&P of Phase I commissioned - Mar, 2011
    • Temporary Housing - Started - Oct 2010, Completed - Jan, 2011
    • Phase-I Production (First coach ready) - 8" April, 2011
    • No. of Permanent Type-ll houses completed - 104
    • No. of Permanent Type-Ill houses completed - 8